-
Stop
Feb 12, 2017
Our last post showed the footings with the wood forms recently removed. Before we could pour the slab within the footings we (the figurative, not literal, 'we') had a number of tasks to complete -- compact soil (within the footings), install underground drain pipes, install under-slab electrical conduit, install downdraft ventilation vent, install structural steel, install under-slab vapor barrier, and install slab rebar. While there were a few problems to solve -- we don't have problems boss, we only have solutions -- our biggest problem was...
...RAIN!
After finishing the footings at the beginning of December 2016, we lost almost 6 weeks due to weather through the first week of February 2017. Back in October 2016, I semi-jokingly told our General Contractor that since we were supposed to get a lot of rain last year during an El Niño condition and didn't, that we would get a lot of rain this year.
We defnitely need the rain in semi-arid Los Angeles which has be suffering from extreme drought conditions over the past few years, but our house construction schedule would look a lot better with less rain during this phase of the build.